client State Building Authority, Augsburg
Construction progress and implementation planning for new, bigger corrugated steel passages for protecting the road embankment in the event of flooding. The existing passages were no longer capable of being renovated. Special attention was paid to the building ground during the planning of the construction sequence and the implementation of the construction. High groundwater levels and less load-bearing soil required close collaboration between the construction ground assessor, the engineering office and the building company carrying out the work.